EAST ST LOUIS ACTION RESEARCH PROJECT

LA/UP341 Fall 1997


Cost and Benefit Breakdown
 
The Bottom Line
Initial Costs           $245,880
Initial Benefits        $56,000
Annual Costs         $12,635
Annual Benefits      $190,181
 
Assumptions  
Initial Costs
Removing rails Cost per unit # of units Total
3 flat bed trucks $1,000 per day 8 days $8,000
crane $1,500 per day 8 days $12,000
people (30) $1,600 per day 8 days $12,800
misc. equipment $300 per day 8 days $2,400
Trail construction
dump trucks and gravel $20 per ton 10256 tons $205,120
people (30) $840 per day 4 days $3,360
misc. equipment $300 per day 4 days $1,200
signage $1,000 $1,000
$245,880
Initial Benefits Benefit per unit # of units
Rail and Tie Salvage $8,000 per mile 7 miles $56,000
Annual Costs Cost per unit # of units Total
Trail Maintenance $375 per mile 7 miles $2625
General Maintenance $1,430 per mile 7 miles $10,010
$12,635
Annual Benefits Benefit per unit # of units
Regional Commercial Benefits
Restaurant $5.21 per person per trip 135000 trips $703,350
Gas $2.14 per person per trip 135000 trips $288,900
Lodging $2.56 per person per trip 135000 trips $345,600
Retail $1.36 per person per trip 135000 trips $183,600
$1,521,450
Adjusted for 6.25% Sales Tax 
and Income Multiplier (2)
$190,181
Project Summary
Initial Costs $245,880
Initial Benefits $56,000
Annual Costs $12,635
Annual Benefits $190,181
Last Update: 11/19/97
-Trail impact data obtained from National Park Service Study & Railtrails.org
-Trail Maintenance data obtained from Wisconsin Department of Natural Resources Bureau of Parks and Recreation